This project utilized a single slug catcher to cover (4) cryo trains being built at the site. Utilizing stock plate, the manifolds arrived on site in just 16 weeks with the total install completed in under 30 weeks.

Location: Lea County, NM

Design: (1) 8-finger slug catcher with double downcomers

Gas Flow: 880 MMSCFD

Storage: 2500bbls

Design Pressure: 1200psig

Specials: 16 week full fabricated manifold delivery

Line Pipe: Stock42” API 5L Line Pipe

Other Project Highlights

Inconel 625 cladded Slug Catcher for the world’s largest operating LNG facility.

One of the largest modular cladded Slug Catchers ever built.

Sour service Slug Catcher.

WHY US

Taylor Forge Engineered Systems
has continued the reputation of traditionally dependable products
to a variety of industries.

Integrity

We don’t compromise our practices and we won’t cut corners.

Collaboration

We take a consultative approach with customers and appreciate the big picture.

Innovation

Setting the standard requires fully understanding the box and when to think outside of it.
Contact Us

We're not around right now. But you can send us an email and we'll get back to you, asap.

Not readable? Change text. captcha txt

Start typing and press Enter to search